Supply agreements and delivery failure: step by step

Supply agreements and delivery failure: step by step comes down to four decisions in order: record the default in writing, set a cure deadline matching the contract, choose between price reduction, cover purchase or termination once that deadline passes, and preserve the paperwork a damages claim will need. Skip a step and remedies narrow, miss a deadline and some disappear.

Who this concerns

This concerns any commercial buyer operating under a supply agreement governed by Swedish law where the counterparty has missed a delivery date, delivered goods that do not conform to the agreed specification, or stopped supplying partway through a framework arrangement. It covers single shipment failures under a one-off purchase contract and recurring shortfalls under a framework agreement with call-off orders, where one missed batch can put the whole production schedule at risk. Manufacturers relying on a single upstream component, distributors carrying a supplier's stock on their own balance sheet, and buyers with a fixed delivery commitment to their own customers all face the same underlying problem: the remedy has to be chosen and documented before the relationship deteriorates further, not after.

The procedure below assumes a business-to-business relationship rather than a consumer sale, and it assumes the buyer wants to keep open the option of damages, price reduction or termination rather than absorbing the loss without response. It applies equally to a contract with a detailed default clause and to one that says almost nothing about what happens when delivery fails, because the steps a buyer needs to take to preserve its position are largely the same either way.

Where the failure is isolated and the relationship is otherwise sound, most of this can be handled internally by procurement and legal. Where the shortfall threatens a customer-facing delivery, involves a supplier already in financial difficulty, or sits inside a longer commercial dispute, it becomes a matter for Lodline's contracts and transactions practice rather than an internal process.

What the law says

A Swedish supply agreement is, first, whatever the parties wrote down. Default and remedy clauses in the contract itself, cure periods, liquidated damages, limits on liability, take priority over background rules, and most disputes over delivery failure turn on how those clauses are drafted rather than on statute. Where the contract is silent or ambiguous, general principles of Swedish contract law fill the gap, under Swedish law as it currently stands, covering when a delay becomes a breach serious enough to justify termination, how a buyer's right to damages sits alongside a right to reduce the price, and what a buyer must do to keep those remedies available rather than lose them through delay or through accepting delivery without reservation.

None of this operates automatically. A buyer that continues to accept deliveries, pay invoices without protest, or simply waits to see whether the supplier catches up risks being treated as having accepted the performance as it stands, which narrows what a court or arbitral tribunal will later accept as a live claim. The notice a buyer sends, and when it sends it, does most of the legal work in this area, and the burden of showing that the notice was timely, specific and properly delivered sits with the buyer, not the supplier.

The picture changes once the supplier sits outside Sweden. The governing law and jurisdiction clause in the agreement, not Swedish default rules, will usually decide where a dispute is heard and in what currency any price adjustment or damages award is expressed, and the practical value of a termination or damages claim then depends on whether the supplier holds assets somewhere a judgment or award can actually be enforced. A claim that succeeds on paper against a supplier with no reachable assets is worth exploring alongside the enforcement question, not after it; see how that question plays out in a jurisdiction such as enforcing an arbitral award in Lithuania for how enforcement constraints shape which remedy is worth pursuing in the first place.

How it works in practice

Step 1: Record the default the day it happens

The clock on most remedies starts running from the date the buyer knew, or should have known, that delivery had failed, not from the date it eventually complains. Record the contractual delivery date, the date nothing arrived or the date the non-conforming goods were rejected, the purchase order or call-off reference, and any communication from the supplier explaining the shortfall. This record becomes the factual basis for the notice in step two and for a damages claim much later, and it is far harder to reconstruct convincingly six months after the event.

Step 2: Send a formal notice with a cure deadline

A notice that merely complains does not preserve remedies; a notice that fixes a deadline does. The notice should identify the contract and the order affected, state what was due and what was received, set a specific date by which the supplier must cure, and state what the buyer intends to do if that date passes: reduce the price, arrange a cover purchase, or terminate. Send it in the form the contract requires, usually in writing to the address or contact specified in the notices clause, and keep proof of delivery.

Step 3: Set a cure deadline that actually matches the contract

If the agreement specifies a cure period, use it: departing from a contractual deadline, even generously, can itself be argued to amend the contract or waive strict compliance. If the agreement is silent, the deadline needs to be long enough to be defensible as reasonable in the circumstances, given the nature of the goods, the supplier's stated reason for the delay, and how urgently the buyer needs the goods, and short enough that it does not read as tacit acceptance of open-ended delay.

Step 4: Decide which remedy to take once the deadline passes

Price reduction keeps the contract alive and suits a shortfall in quality rather than quantity. A cover purchase, buying the same or equivalent goods elsewhere and charging the difference to the supplier, suits a case where the goods are needed regardless of the dispute and are available from another source. Termination suits a breach serious enough that continuing the relationship no longer makes commercial sense, but it ends the contract for both parties and forecloses any argument that the buyer waived the breach by continuing to perform. The choice should be made once, in writing, rather than left open while the buyer decides what to do next.

Step 5: Gather the documents a damages claim will need

Whichever remedy is chosen, the file needs to show the contract and any amendments, the purchase order or call-off, the delivery records or non-conformity report, the notice and cure deadline, evidence of any cover purchase including quotes obtained from alternative suppliers, and any internal correspondence showing the operational impact: lost production time, a customer contract missed, a penalty incurred downstream. A damages claim without contemporaneous evidence of loss is difficult to sustain even where liability is not seriously contested.

Step 6: Escalate only once the position is fully documented

If the supplier disputes the default, disputes the remedy chosen, or simply does not respond, the file built in steps one through five becomes the basis for either a formal demand through counsel or, where the contract requires it, referral to arbitration or the courts named in the dispute resolution clause. Escalating with a partial file, a notice with no proof of delivery attached, a damages estimate with no supporting quotes, tends to cost more time than waiting a further week to complete it, because a tribunal or counterparty's counsel will test the file's completeness before testing its substance.

What to check before the notice goes out

  • The governing law and jurisdiction or arbitration clause, and whether the notices clause specifies a particular form or address.
  • Whether the contract defines "delivery" by dispatch, arrival, or acceptance, since this fixes when the default actually occurred.
  • Any condition precedent to a remedy, such as a requirement to notify within a fixed period or to allow a specified number of cure attempts.
  • Any liability cap or exclusion that limits what a damages claim can realistically recover.
  • Whether related call-off orders under the same framework agreement are affected, or only the one shipment.
  • The language and currency the contract specifies for notices and for any price adjustment, particularly where the supplier is based outside Sweden.

How long does a supplier usually have to cure a missed delivery?

That depends on the contract. Where the agreement sets a cure period, that period controls, and departing from it risks being read as a variation of the contract. Where the agreement is silent, the deadline needs to be reasonable given the type of goods, the reason given for the delay, and the buyer's actual operational need, rather than fixed at a standard number of days; what counts as reasonable is assessed on the facts of the individual contract, not read off a general rule.

What happens if the buyer keeps accepting late deliveries without objection?

Continuing to accept deliveries and pay invoices without reservation is commonly treated as accepting the supplier's performance as it stands, which can narrow the remedies later available for the same pattern of delay. A buyer that wants to keep its options open should say so in writing at the point of each late or non-conforming delivery, rather than waiting until the relationship breaks down entirely to raise it.

Can a cover purchase be charged back to the supplier automatically?

No. A cover purchase needs to be reasonable in its own right, made without unnecessary delay, at a price that reflects the market rather than convenience, and properly evidenced with quotes or purchase records. A buyer that overpays for a rushed replacement, or delays the cover purchase without good reason, risks having the difference disallowed later even where the underlying default is not disputed.

The numbers

The concrete deadlines that matter in a delivery failure are set by the contract, not by a statutory default: the cure period in the default clause, the notice period attached to termination, and any liquidated damages formula, usually expressed as a percentage of the value of the delayed shipment or of the contract as a whole, and often capped. Where the contract does not fix a cure period, Swedish general contract law does not substitute a single numeric deadline; it asks what period was reasonable given the goods and the circumstances, which is a question of fact rather than a fixed number of days.

What can be estimated before the notice is even sent is the exposure on both sides: the value of the undelivered or non-conforming goods, the incremental cost of sourcing the same goods from an alternative supplier at current market prices, and any downstream cost, a missed customer deadline, idle production capacity, that a damages claim would need to itemise. None of these figures is fixed by law; each depends on the market at the time and on how well the buyer documents the impact in step five above. A liability cap, where the contract contains one, usually applies to the damages figure rather than to the price reduction or the cover purchase claim, and the two need to be kept analytically separate when the file is put together.

Where the underlying agreement is a long-term supply or framework contract tied to a construction or infrastructure programme, a single missed delivery rarely stays isolated: it tends to interact with the change and variation mechanism in the wider project contract. See how that interaction is handled in changes to an infrastructure procurement contract for how a delivery failure further down the chain can trigger a formal change process further up it.

Where it usually goes wrong

The most common failure is sequencing: sending a termination letter before a proper cure notice has run its course, which gives the supplier grounds to argue the termination itself was premature and therefore wrongful. The second most common failure is silence: continuing to accept partial or late deliveries for months without any written reservation, then trying to rely on the original default once the relationship finally breaks down.

A cure deadline that is unrealistically short for the type of goods involved, raw materials with a long lead time, custom-manufactured components, undermines the notice that contains it and can be challenged as not reasonable in the circumstances, which in turn weakens any remedy that follows from the deadline passing unmet.

Where the supply agreement contains an arbitration clause, a buyer that goes straight to a demand letter threatening court proceedings, without checking the dispute resolution clause, can find itself arguing the wrong forum from the outset, a mistake that is expensive to unwind once the other side raises it. Where an award or judgment is later obtained but the supplier's assets sit outside Sweden, the practical question of whether that outcome can be enforced needs to be asked before the claim is filed, not after; the same issue arises in reverse when a supplier later tries to challenge an arbitral award obtained against it, and the evidence a buyer secures at step one is exactly what determines whether that challenge succeeds.

Finally, a delivery failure surfacing during an ongoing commercial negotiation, an earn-out period following an acquisition, a renegotiation of pricing, is often treated as a routine default when it is actually part of a wider dispute about the underlying deal; the applicable regime and the remedies available can differ substantially, as set out in earn-out disputes after closing.

What to do next

The steps above get a buyer to a documented default, a defensible notice, and a chosen remedy. They do not replace a read of the actual contract, the correspondence already sent, and the commercial context, all of which change what a lawyer would recommend in a specific case. Where a delivery failure surfaces during due diligence on an acquisition or asset transfer, the underlying supply agreement needs the same scrutiny as any other assumed liability; see what an asset deal typically costs and how it plays out for how that review is scoped. For a specific default already in progress, book a preliminary assessment before the next notice goes out, not after.