Supply agreements and delivery failure: what to do in the first ten days

Supply agreements and delivery failure: what to do in the first ten days comes down to three moves, not legal theory: fix the breach in writing, check what the contract itself says about cure and termination, and start a record that will still hold up if the matter reaches a Swedish court or arbitral tribunal later. Miss any of the three and the strongest substantive claim gets weaker for reasons that have nothing to do with the merits.

Who this concerns

This situation arises for procurement teams, commercial managers and in-house counsel on either side of a Swedish-law supply agreement once a delivery is late, partial, off-specification, or stopped altogether. It applies whether the buyer is a manufacturer waiting on components, a retailer waiting on stock, or an infrastructure operator waiting on equipment tied to a project schedule. It applies equally to the supplier receiving a claim of failure, because the same ten-day window is when a badly drafted notice, or one sent to the wrong address under the contract, can be challenged on procedural grounds regardless of whether the underlying breach happened.

The broader mechanics of how supply and delivery obligations sit within Swedish commercial contracts more generally are set out on the contracts and transactions practice page. What follows here is narrower: the sequence that matters in the first ten calendar days after a delivery failure is identified.

What the law says

Under Swedish law as it currently stands, delivery failure under a supply agreement is governed first by what the parties wrote into the contract, and only residually by background statutory defaults. Where the agreement is silent or unclear, general principles of Swedish contract and sales law fill the gap. A buyer facing a proven breach typically has a menu of responses available: demanding performance, withholding payment proportionate to the shortfall, claiming a price reduction, claiming damages for loss caused by the delay, and, where the breach is serious enough, terminating the agreement. None of these responses is automatic. Each carries its own threshold, its own notice requirement, and its own consequence if exercised on the wrong facts.

A point that surfaces constantly at the ten-day mark is the difference between characterising the failure as a delay in delivery and characterising it as a defect in what was actually delivered. The remedies attached to each differ, and a notice drafted around the wrong characterisation can undermine the buyer's negotiating position later, even where the underlying commercial complaint was legitimate from day one.

It is also common, once a delivery problem surfaces, for the supplier to respond by asking for anstånd, a grace period to complete the delivery on revised terms. Granting anstånd does not happen automatically and does not, on its own, suspend the buyer's other remedies unless the buyer agrees to that in terms that say so explicitly. Treating an informal request for more time as if it were a binding extension is one of the more common ways a buyer's position weakens in week two.

How it works in practice

Day one: fix the breach in writing

The first written notice should identify the specific delivery obligation that was missed, the date and quantity or specification involved, and the clause of the contract it relates to, if the contract numbers its obligations. A notice sent by informal email with no reference to the contract's own notice mechanism is often valid in principle but weaker in practice, because it gives the supplier room to argue later that the "real" notice, the one that started any contractual clock, never arrived in the form the contract requires.

Days two to four: check the contract before reacting further

Before anything else goes out, the contract itself needs to be checked for four things: the notice clause, including how notice must be delivered and to whom; any cure period the supplier is entitled to before the buyer can treat the failure as a termination event; any force majeure or hardship clause the supplier might invoke; and the governing law and dispute resolution clause, particularly where either party sits outside Sweden. Skipping this step and moving straight to a demand or a threat of termination is the single most reversible mistake available in the first week, and also the easiest one to avoid.

What to preserve from day one

Delivery logs, quality inspection reports, photographs of the goods as received, internal correspondence discussing the impact of the failure, and any cost incurred in sourcing a replacement or cover supply should all be kept from the first day, not assembled retrospectively once a dispute looks likely. How this kind of evidence holds up months later, once a claim has moved into a dispute forum, is covered in the practice's separate material on evidence handling in arbitration and litigation. The short version for the first ten days: assume every document created now will be read out of context later, and write accordingly.

Days five to seven: choosing which remedy to press

By the end of the first week, the buyer usually needs to decide whether it is heading toward a damages claim, a termination, or a negotiated adjustment such as a price reduction combined with a revised delivery date. This decision is not neutral. Terminating commits the buyer to treating the contract as at an end, which closes off some remedies and opens others; pressing for performance keeps the relationship alive but can undercut a later argument that the breach was serious enough to justify termination. The choice should track what the buyer actually wants at the end of the process, not just what feels justified on day five.

Days eight to ten: the cure window and what happens if it is missed

If the contract gives the supplier a defined period to cure the failure, that period runs from whenever the contract says it runs, not from when the buyer feels enough time has passed. Where the supplier misses the cure window, the buyer's options typically widen: termination becomes easier to justify, and any damages claim gains a cleaner factual basis. Where the supplier asks for anstånd instead of curing within the window, the buyer's response to that request should itself be in writing and should state clearly whether other remedies are being reserved.

Where the foreign element changes the sequence

Where the supplier, the buyer, or a parent company sits outside Sweden, the ten-day sequence above still applies, but three things change. First, the governing law clause needs confirming before assuming Swedish rules apply at all; a supply agreement between a Swedish buyer and a foreign supplier does not automatically sit under Swedish law just because the buyer is Swedish. Second, notice delivery needs to account for time zones, local public holidays, and, in some cases, a translation requirement built into the contract itself. Third, any eventual enforcement step, whether a judgment or an arbitral award, will need to be recognised in the supplier's home jurisdiction, which is a separate question from whether the breach occurred. Similar timing pressure shows up in adjacent situations, such as where a procurement contract change on an infrastructure project needs formal documentation before work can continue; the underlying discipline, get it in writing before acting, is the same.

What to check

  • The notice clause: form, recipient, and method of delivery required by the contract.
  • The cure period: whether one exists, how long it runs, and from what trigger event.
  • The force majeure or hardship clause: whether the supplier has a live argument available.
  • The limitation of liability clause: what it caps, and whether it caps the specific loss being claimed.
  • The governing law and dispute resolution clause: whether it is Swedish law and a Swedish forum at all.
  • Any insurance or cover clause: whether replacement sourcing costs are recoverable under the contract's own terms.
  • The termination trigger: what threshold of breach the contract requires before termination is available.

Supply arrangements built around standard construction terms raise a related question, covered separately in the material on construction contracts under AB 04 and ABT 06, where delivery failure sits inside a broader project schedule rather than a single shipment.

What buyers and suppliers usually ask in the first ten days

What evidence should be preserved if a delivery dispute proceeds to arbitration or court?

Delivery logs, inspection records, all correspondence with the supplier, and documented mitigation costs such as cover purchases should be kept from day one. What matters most later is contemporaneous documentation created before the dispute was anticipated, not material assembled after the fact once litigation looks likely.

What does anstånd mean when a supplier asks for more time to deliver?

Anstånd is a grace period the supplier requests to complete an outstanding obligation. It is not automatic and does not suspend the buyer's other remedies unless the buyer agrees to specific terms confirming that it does. A verbal or informal agreement to anstånd should always be confirmed in writing before either side relies on it.

Does the same first-ten-days approach apply to supply obligations under AB 04 or ABT 06?

The underlying discipline, notice in writing, checking the contract's own cure mechanics, and preserving evidence, applies in both contexts. Construction contracts under AB 04 and ABT 06 add their own notice and remedy structure layered on top of general contract principles, which needs checking separately from a standalone supply agreement.

The numbers

Swedish law as it currently stands does not impose a single fixed statutory notice period for reporting a delivery failure under a commercial supply agreement outside consumer sales. Timing is set primarily by what the contract itself specifies for notice and cure, supplemented by a general expectation that a party acts without undue delay once it discovers, or should have discovered, the breach. Where the contract sets a specific number of days for notice or cure, that figure controls; where it does not, "without undue delay" is assessed against the facts of the individual case rather than a fixed rule.

The cost of building a defensible file in the first ten days is similarly not a fixed figure. It depends on how many shipments or deliveries are affected, whether records need to be gathered from multiple sites or from a foreign supplier's own systems, and whether the dispute is likely to stay commercial or move toward arbitration or litigation. What increases cost predictably is scale, cross-border evidence gathering, and any need to reconstruct a timeline that was not documented contemporaneously.

Where it usually goes wrong

The most common failure is sending an informal complaint instead of a notice that tracks the contract's own notice clause, which can later be challenged as never having triggered the contractual cure or termination mechanism at all. A close second is terminating before checking whether a cure period applies, which exposes the terminating party to a wrongful termination claim of its own, effectively reversing who is in breach.

Mixing up delay and defect characterisation causes problems that surface weeks later, when the remedy actually available turns out to differ from the one assumed at the outset. Failing to document mitigation, such as a cover purchase made to keep operations running, weakens a later damages claim even where the underlying loss was real and substantial.

In cross-border supply relationships, the most damaging mistake is proceeding on the assumption that Swedish law and Swedish courts apply without checking the governing law and dispute resolution clause first. Where that clause points elsewhere, the entire first-ten-days sequence described here needs to be re-run against a different legal framework before any notice goes out. And where a supplier's request for anstånd is treated as a binding extension without written confirmation, the buyer can find that remedies it assumed were preserved were, in the supplier's view, given up by conduct.

What to do next

This material gets a buyer or supplier to a defensible file inside the first ten days: notice sent correctly, cure mechanics checked, evidence preserved, remedy choice made deliberately rather than by default. It does not replace a read of the specific contract wording, and in particular the clause that usually decides what a claim is actually worth once the ten-day file is complete: the limitation of liability clause, which caps or excludes categories of loss and often determines whether pursuing a remedy is worth the cost of pursuing it.